Facilities Management has scheduled elevator modernization improvements to the Founders Hall, University Center Quad and Siemens Hall elevators. 

The Founders Hall elevator modernization is continuing and expected to be completed between September 14th-18th. The University Center Quad elevator will begin on Wednesday, August 19th with an estimated completion date of September 9th. The Siemens Hall elevator will begin upon completion of the UC Quad elevator and is estimated to be complete by the last week of September. 

During the modernization work, the above listed elevators will be out of service. Students, faculty and staff needing elevator access can contact the Student Disability Resource Center at 707-826-4678 or Human Resources at 707-826-3626 for help with access.

 Please feel free to contact Bruce Ryan, Facilities Project Manager, at 707-599-6463 with any questions or concerns.