Construction Update: Forbes Gym, Rec & Wellness Center
August 20, 2013
The exterior painting of the Recreation & Wellness Center and Forbes is almost complete! The painting contractor is wrapping up this phase, and they will revisit the project to touch up after the roofing has occurred. We are very pleased with the results so far, and hope you are too. The Reroof Project for Forbes Complex is ramping up, and we will continue to see an increase in activity. We have installed fencing to contain the construction areas, but ADA & Pedestrian access though the construction area will be maintained. The roofing contractor has begun on the flat roofs over the open air lobby and Forbes equipment rooms; they will begin on the Forbes Gym roof next week. Construction will continue through mid-October. We will work to minimize the impact on classes, activities, practices, and foot traffic, and we greatly appreciate your patience & cooperation. Please contact me at x5902 or 267-4592 with any concerns or comments.Zach SheltonConstruction Manager